Project management panels

$
0
0

Procuring a project manager

A project manager must be nominated for all school property projects. As a board of trustees, you must engage a professional project manager if your project needs building consent. See Project manager engagement for full details. We recommend you engage a project manager from one of the panels.

Establishment of the panels

The panels have been established through a robust procurement process in line with Government rules and regulations. Selection criteria for the panels included experience and qualifications as well as references and understanding of health and safety requirements. A key aim of the panels is to improve the quality of services that schools receive. 

Deciding which panel to use

There are different panels for minor services and major services.

Panel

Value of individual construction/capital project

Project Management - Minor Services

Up to $500K

Project Management - Major Services (3 sub panels)

$500K to $2 million

$2 million to $10 million

$10 million plus

 

Due to the range of project values, risk and complexity of school projects we created 2 panels to reflect the different requirements (skills, qualifications and experience) of suppliers to provide these services. 

To help you decide which panel to use follow this flow chart:
Panel Selection Flowchart
If you have trouble using the databases in the Project Management Panels, email property.help@education.govt.nz.

Getting quotes using the Project Management Minor Panel

Where the total service fee is less than $50,000, you must obtain at least one quote from a supplier on the list.

Where the total service fee is greater than $50,000 you must obtain at least 3 quotes from a supplier on the list.

However, to get a good comparison we recommend you obtain a minimum of 3 quotes whenever engaging a project manager.

Send your Project Management Minor Services Request for Quote (RFQ) documentation to the suppliers you selected to quote. The documentation must contain:

Note: Your supplier can also tender to be your 10 Year Property Plan (10YPP) Consultant. But they must go through a separate procurement process and have a separate contract for this work.

Getting quotes using the Project Management Major Services Panel

Once you have decided which sub-panel to use identify the suppliers which you intend to request quotes from. Contact your local Ministry property advisor if you need help to choose which suppliers you should ask to quote. 

When using this panel you must obtain at least 3 quotes from a supplier on the list.

Send your Project Management Major Services Request for Quote (RFQ) documentation to the suppliers you selected to quote. The documentation must contain: